    SCOPE OF WORK

    CME Civil were awarded several packages as part of the Oaklands Crossing Grade Separation Project. Works involved construction of rail formation (subgrade cut/fill/trim including capping construction for final rail formation), rail corridor drainage pipework & infrastructure and supply/install of OLE gantry footings/piles in sequence with rail corridor drainage and formation construction, construction of new granular road pavements including new stormwater drainage and modifications of existing, road lighting and traffic signals infrastructure (i.e. conduits, pits, pole footings), construction of stage 2 car parks (3x new carparks), footpaths and kerbing.

    CLIENT
    McConnell Dowell Pty Ltd

    LOCATION
    Oaklands Park, SA, 5046

    PROJECT VALUE
    $5 Million

    CONSTRUCTION PERIOD
    June 2018 – July 2019